Fluvius Ghent
Close
Fluvius Ghent

A sustainable business site for Fluvius in Ghent

 

At the end of 2023, grid operator Fluvius moved to its new site at The Loop in Ghent, a build-to-suit project by ION. The office building, warehouse, and outdoor storage are home to the nearly 150 employees of the Fluvius Scheldt-Lieve region.

Units
10
Address

Poortakkerstraat - 9000 Ghent

Investment value
+20 million euros
Surface
6.460 m²
Architects
Wielfaert Architects
Partners
Building company Mathieu Gijbels, Fluvius, Sweco
Sustainability as a core value

ION applied a very ambitious sustainability standard for this development. The project complied with the regulations of the Flemish government's GRO sustainability tool, striving for a performance level that was 20% higher than the EPB legislation in force when ION submitted its application for planning permission.

Optimal mobility

Employees can reach Ghent and the fringe of the vast catchment area from the new location for interventions quickly and without detours. There is a bus and tram stop less than a kilometre from the site, and the Gent-Sint-Pieters railway station is less than three kilometres on foot. The site can also be reached quickly and efficiently by bicycle.

Innovative construction methods

Construction company Mathieu Gijbels, which uses advanced technologies to build as efficiently as possible, was in charge of building the new site. They used BIM (Building Information Modelling) to create a 3D digital representation of all the characteristics of the new regional building.

Build to suit: customisation in practice

The 'Build-to-suit' partnership between ION and Fluvius is an excellent example of customisation. ION created a solution that meets Fluvius's requirements and reflects its vision of sustainability, mobility, and community engagement. The result attests to ION's flexibility and ability to tailor each project to the client's needs.

A sustainable approach

The project complies with the regulations of the Flemish government's GRO sustainability tool, striving for a performance level that was 20% higher than the EPB legislation in force when ION submitted its application for planning permission. Energy monitoring and water reuse are also essential aspects of this design concept. An integrated green design is conducive to a harmonious working environment.

Triple A location

The project's location on Poortakkerstraat on the outskirts of Ghent guarantees excellent accessibility for both employees and visitors. The Loop is well connected, with bus and tram stops less than a kilometre on foot, a railway station less than three kilometres from the site, and access to an extensive network of cycle paths and highways. During construction, a new cycle path was constructed that runs parallel to the site.

Cijfers van dit project

  • Terreinoppervlakte: 7.703 
  • Kantoorgebouw: 3.680 
  • Magazijn: 1.735 
  • Buitenopslag: 1.130 
  • Ondergrondse parking: 63 parkeerplaatsen (ca. 2.400 m²)
  • Bovengrondse parking: 2 parkeerplaatsen
The Build-to-Suit collaboration between ION and Fluvius is an example of customized action.
“I’m delighted with Fluvius’ arrival in The Loop. We’re designing a new futuristic district at this readily accessible site, with space not only designated for offices; but also retail, leisure, parks, housing and public facilities. This combination of amenities will make for a vibrant city district.”

- Mathias De Clercq, City of Ghent Mayor

Innovative construction methods

Construction company Mathieu Gijbels, which uses advanced technologies for all its projects, including Building Information Modelling (BIM), was tasked with the construction. BIM can be used to anticipate potential conflicts as early as the design phase,  ensuring the construction process is more efficient and seamless and in keeping with the predetermined timing and budget.

The brand-new four-storey office building has a 2,500-m2 underground parking garage. A 2,000-m2 steel structure was built alongside the office building, with concrete panels and a green roof, for use as a warehouse. The project is in a flood-prone area, so a floodable crawl space was built under the warehouse.

Got a construction project of your own? Discover ION as a one stop shop.

Request more information

Fill in your information and we will get you an answer quickly.
  • Discover our references